Process Areas for CMMI ML2:

REQUIREMENTS MANAGEMENT (RM)

PROJECT PLANNING (PP)

PROJECT MONITORING AND CONTROL (PMC)

Supplier Agreement Management (SAM)

Measurement and Analysis (MA)

PROCESS AND PRODUCT QUALITY ASSURANCE (PPQA)

CONFIGURATION MANAGEMENT (CM)

PA: CONFIGURATION MANAGEMENT (CM)

3 specific goals (SG) and 1 generic goal (GG)

SG1: Baselines of identified work products are established and maintained.

Practice Goal & Practice Statements Document Evidence
SP 1.1 Identify the configuration items, components, and related work products that will be placed under configuration management. ¡@
SP 1.2 Establish and maintain a configuration management and change management system for controlling work products. ¡@
SP 1.3 Create or release baselines for internal use and for delivery to the customer. ¡@

SG2: Changes to the work products under configuration management are tracked and controlled.

Practice Goal & Practice Statements Document Evidence
SP 2.1 Track change requests for the configuration items. ¡@
SP 2.2 Control changes to the configuration items. ¡@

SG3: Integrity of baselines is established and maintained.

Practice Goal & Practice Statements Document Evidence
SP 3.1 Establish and maintain records describing configuration items. ¡@
SP 3.2 Perform configuration audits to maintain integrity of the configuration baselines. ¡@

GG2: The process is institutionalized as a managed process.

Practice Goal & Practice Statements Document Evidence
GP 2.1 (CO 1) Establish and maintain an organizational policy for planning and per-forming the configuration management process. ¡@
GP 2.2 (AB 1) Establish and maintain plan for performing the configuration management process. ¡@
GP 2.3 (AB 2) Provide adequate resources for performing the planned process, devel-oping the work products and providing the services for the configura-tion management process. ¡@
GP 2.4 (AB 3) Assign responsibility and authority for performing the process, devel-oping the work products, and providing the services of the configura-tion management process. ¡@
GP 2.5 (AB 4) Train the people performing or supporting the configuration manage-ment process as needed. ¡@
GP 2.6 (DI 1) Place designated work products of the configuration management proc-ess under appropriate levels of configuration management. ¡@
GP 2.7 (DI 2) Identify and involve the relevant stakeholders of the configuration man-agement process as planned. ¡@
GP 2.8 (DI 3) Monitor and control the configuration management process against the plan for performing the process and take appropriate corrective action. ¡@
GP 2.9 (VE 1) Objectively evaluate adherence of the configuration management process against its process description, standards, and procedures, and address noncompliance. ¡@
GP 2.10 (VE 2) Review the activities, status, and results of the configuration manage-ment process with management and resolve issues. ¡@

¡@

Common features of the generic practices:

Back to Top

¡@